Villa renovation in Emirates Hills — Emaar first, then DDA.
In Emirates Hills, villa work beyond routine maintenance and repair needs an Emaar NOC first, then a DDA Building Modification permit, and a completion sign-off at the end. Emaar’s standard NOC factsheet excludes Emirates Hills, so the fees differ from its other communities: on our 2026 applications, AED 500 to apply and a refundable AED 10,000 deposit.
Last reviewed 16 Oct 2026Sources and dates

At a glance
Emirates Hills, at a glance.
Approvals · Emirates Hills
The Emirates Hills approval route, in six steps.
Emaar reviews the villa alteration first; DDA then approves the design, issues the permit and signs off completion. The fees are Emaar’s Emirates Hills figures, not its standard factsheet.
Step 01 / 06
Survey the house as built
- Issued by
- Fajr Interiors, at the site survey
- Where
- Your villa
- You receive
- Measured drawings, the scope and the documents list
What to know
Emirates Hills homes were custom-built on their plots,2 so there is no standard type plan to start from. We measure the house and record earlier changes before anything is drawn.
Step 02 / 06

Emaar NOC
- Issued by
- Emaar
- Where
- Community portal → Home Modifications
- You receive
- The Emaar NOC for the works
Step 03 / 06


DDA Building Modification – Design
- Issued by
- DDA; the consultant applies
- You receive
- Stamped, approved drawings
What to know
DDA asks for the approved drawings, the proposed changes highlighted, structural calculations where relevant, and a Dubai Civil Defence NOC where fire and life safety systems change.8
Step 04 / 06

DDA Building Modification – Permit
- Issued by
- DDA; the contractor applies
- You receive
- The building modification permit
What to know
Charged per square foot of added or relevant built-up area, with an appointment letter signed by the owner, consultant and contractor.9
Step 05 / 06

ECM contractor entry permit
- Issued by
- Emaar Community Management
- Where
- ecmpermits.ae
- You receive
- An entry permit for Emirates Living and this contract
Step 06 / 06



Completion, then the deposit
- Issued by
- Emaar, then DDA
- Where
- Community portal; DDA Building Modification – Completion
- You receive
- Emaar’s sign-off, the DDA completion certificate and the deposit back
Read the detailClose the detail
Emirates Hills is one of five communities in Emirates Living, with The Springs, The Meadows, The Lakes and Hattan.3 It shares their rulebook and their contractor permits, but not Emaar’s standard NOC service: the factsheet says that service is not applicable to Emirates Hills.1 That is why the review fees and times published for other Emaar villas do not appear on this page.
The order on our 2026 applications was Emaar’s NOC first, then DDA.17 We lodge the Emaar submission as soon as the layout is signed, so the DDA design review runs inside the 8-week design stage.
Documents
What goes into an Emirates Hills submission.
Emaar reviews detailed plans; DDA adds its own lists for design, permit and completion. We assemble both from one survey.
Concept visualisationYou provide
- Title deed and owner ID
- The villa’s approved drawings, if you hold them8
- Earlier NOCs, if the villa has been altered
We prepare
Read the detailClose the detail
A DDA design application starts from the approved drawings of the villa as built.8 A custom house may have been altered since its first approval, so the survey measures what stands rather than trusting an old set.
Fees and timelines
Fees and timelines for an Emirates Hills villa.
Emaar’s figures from our own 2026 applications, and DDA’s published fees, each dated. Confirm every one at application.
The villa programmeAround 12 months, brief to handover
| Item | Figure | Timing | Charged by | Source |
|---|---|---|---|---|
| Emaar NOC · application fee | AED 500 | Paid when you apply | Emaar | From Fajr’s 2026 applications; estimated, not an official schedule. Source 17. Confirm at application. |
| Security deposit | AED 10,000, refundable | Refund terms confirmed with Emaar at application | Emaar | From Fajr’s 2026 applications; estimated, not an official schedule. Source 17. Confirm at application. |
| Extension fee · added BUA | AED 1,000 per sq ft | Charged on the added area; each extension assessed case by case | Emaar | From Fajr’s 2026 applications; estimated, not an official schedule. Source 17. Confirm at application. |
| Emaar’s standard NOC fees | Not applicable: the factsheet excludes Emirates Hills | Its published review times do not apply either | Emaar | As published by Emaar, April 2022. Source 1. Confirm at application. |
| DDA Building Modification – Design | AED 1,500 + AED 10 Knowledge + AED 10 Innovation Dirham | 5 working days; approved design valid 6 months | DDA | As published by DDA, September 2026. Source 8. Confirm at application. |
| DDA Building Modification – Permit | AED 1 per sq ft of added or relevant BUA + AED 20 | 2 working days; renewal AED 200 per 3 months, up to 1 year | DDA | As published by DDA, September 2026. Source 9. Confirm at application. |
| DDA Building Modification – Completion | No fee for a standard submission | 3 working days | DDA | As published by DDA, September 2026. Source 10. Confirm at application. |
Read the detailClose the detail
Emaar does not publish an Emirates Hills fee schedule. Its standard factsheet excludes the community,1 so the AED 500 application fee, the AED 10,000 deposit and the AED 1,000 per sq ft extension fee come from our 2026 applications.17 We ask Emaar to confirm each in writing with the application.
DDA’s pages are undated, so they show the month we read them.
What’s allowed
What you can change in an Emirates Hills villa, and what needs Emaar.
The Emirates Living rulebook and ECM’s guidelines, in three states. Each chip links to its source.
Allowed without an NOC3
Needs approval first7
Read the detailClose the detail
An extension needs Emaar’s prior approval and settlement of its charges.6 On our 2026 applications that charge was AED 1,000 per sq ft of added area.17 Emaar assesses each extension case by case, so it is drawn and put to Emaar before it is priced.
ECM’s guidelines for Emirates Living prohibit exterior alterations, doors and windows included.5 They are written for the whole master community, and Emirates Hills homes are custom-built, so we put every exterior item to Emaar in writing before it is drawn.
Rules on site
Rules on site in Emirates Hills.
The Emirates Living villa rulebook, uploaded in February 2026, sets the hours below. Noisy work outside them earns a notice of violation.
The working daySource 6
- Monworks
- Tueworks
- Wedworks
- Thuworks
- Friworks
- Satworks
- Sunno works
Entry permits
Contractors enter only with approved entry permits; the community manager can refuse access.6
Deliveries
48 hours’ notice for bulk deliveries, Monday to Saturday, 10:00–13:00; none on public holidays.6
Noise
Excessive if a neighbour can hear it inside their home; some works need neighbours’ NOCs.6
NOC on display
The NOC is displayed on site during the works and kept with the property records.6
Common areas
Dust controlled, paths protected while materials move, fire-alarm devices covered.6
Penalties
Work without an NOC brings a notice of violation; fines go on the owner’s service-fee account.6
Read the detailClose the detail
ECM’s contractor portal gives different hours, 08:00 to 17:30 with Fridays off.7 The villa rulebook is the newer document and names Sundays as the rest day, so we plan to it and confirm with the community office at mobilisation. Ramadan hours are not stated in the rulebook.
Villa types
Emirates Hills villa types, and what each usually needs.
Most Emirates Hills homes were built to their owners’ own designs, so the type is a starting point. The survey reads the house itself.
Custom-built villas on owners’ plots
Sectors E, H, L, P, R and W
- Bedrooms
- 5–7+ bed
- Handover
- Late 2000s16
Typical renovationWhole-house remodels with new services, phased by floor; any extension drawn for Emaar first.
Emaar-built villas, an original type
Signature Villas
- Bedrooms
- 5–7 bed
- Handover
- Not published12
Typical renovationReception rooms and kitchens replanned; stone, joinery and lighting renewed.
Traditional Arabic-style villas
Dyaar Al Hambra
- Bedrooms
- From 5,400 sq ft
- Handover
- Released 200511
Typical renovationMajlis and family rooms re-planned inside the existing exterior.
Maisonettes, a few semi-detached
Montgomerie Maisonettes
- Bedrooms
- 3–4 bed
- Handover
- Released 200511
Typical renovationKitchens and bathrooms renewed; party-wall work planned with the neighbour.
On the Montgomerie fairways
Golf-course villas
- Bedrooms
- 5–7 bed
- Handover
- Not published12
Typical renovationTerraces and glazing kept as built; rooms replanned toward the course.
Around the 17 lakes
Lake-facing villas
- Bedrooms
- 5–7 bed
- Handover
- Not published2
Typical renovationPool and terrace joined to the living rooms; waterproofing checked first.
Read the detailClose the detail
A 2014 portal article names three original types, Al Hambra, Signature Villas and Montgomerie Maisonettes, built in Traditional Islamic, Contemporary Modern and Classic European styles, and counts 250 course-facing villas.12 Gulf News reported the Maisonettes and Dyaar Al Hambra released in 2005.11
Portals name Sectors E, H, L, P, R and W; we found no full list of sectors from Emaar.1415 Bedroom counts come from portals, not Emaar; one cites land department records showing most villas at 5 to 7 bedrooms.13
Common projects
What Emirates Hills owners ask us to change.
Large custom houses, many from the 2000s: services, stone and the garden, at a scale that is phased rather than rushed.
Concept visualisationServices at house scale
AC plant, ducting and plumbing in a large villa are renewed with the ceilings open, sized for the house as replanned, not patched room by room.
Concept visualisationStone chosen from samples
Stone and joinery for a house this size carry long lead times, so they are approved from samples while Emaar and DDA review the drawings.
- Pool to house
Lakes and fairways
Most homes overlook a lake, the fairways or parkland.2 Pools and terraces need written approval,6 so we draw the garden with the house.

Extensions, priced per sq ft
On our 2026 applications Emaar charged AED 1,000 per sq ft of added area.17 We draw the extension and put it to Emaar before it is priced.
- Mature gardens
Mature trees stay
Mature planting often sits where new terraces would go. No tree comes out without written permission.6
Design renders
Mansion-scale rooms, tested in renders first.
Fajr Interiors design renders from our villa design sets, not photographs of a villa in Emirates Hills. Rooms are agreed on screen and on samples while the approvals are in review.

RenderMedia wall with a linear fire and walnut shelving 
RenderLiving room, with the dining table and kitchen beyond 
RenderThe dining table, seen from the landing 
RenderLiving corner, fluted panels and a triptych
Renders, not photographs. Tap a render to enlarge it.
Villa 47 Fairways, a finished villa in Dubai Hills →Cost
What an Emirates Hills renovation costs.
Villa renovation in Dubai runs AED 420–1,400 per sqft of built-up area, and our villa budgets start from AED 1M. In Emirates Hills the built-up area, the finishes and any extension decide the figure; an extension adds Emaar’s charge on the added area. Your number is a line-by-line quote against drawings, never a rate.
Emirates Hills FAQ
Before you renovate in Emirates Hills.
Villa renovation FAQ — Emirates Hills, Dubai.
The questions Emirates Hills owners ask before a survey, answered from Emaar’s, ECM’s and DDA’s own pages and our 2026 applications.
01Do I need an Emaar NOC to renovate my villa in Emirates Hills?
Yes, for anything beyond routine maintenance and repair. The Emirates Living rulebook, which covers Emirates Hills, requires detailed plans and the Community Manager’s written approval before works start, and the NOC stays on display on site. Work without an NOC brings a notice of violation and fines on the service-fee account.
02Which authority issues the building permit for an Emirates Hills villa?
The Dubai Development Authority, after the Emaar NOC; that was the order on our 2026 applications. The consultant applies for DDA Building Modification – Design and the contractor for the permit. Dubai Civil Defence joins only where fire and life safety systems change, and DDA closes the job with a completion certificate.
03What does Emaar charge for a modification in Emirates Hills?
Emaar’s standard factsheet excludes Emirates Hills, so its usual fees do not apply. On our 2026 applications Emaar charged a AED 500 application fee and took a refundable AED 10,000 deposit; an extension added AED 1,000 per sq ft of new area. DDA charges its own published design and permit fees on top.
04Can I extend my villa in Emirates Hills?
Yes, with Emaar’s prior approval, and its charges must be settled first. On our 2026 applications the charge was AED 1,000 per sq ft of added area. Emaar assesses each extension case by case, so we draw it and put it to Emaar before pricing, then DDA issues the permit.
05Can I change the exterior of my Emirates Hills villa?
ECM’s Emirates Living guidelines prohibit exterior alterations, including doors, windows and window coverings, and the rulebook bans visible solar panels and outdoor AC units on the façade. Emirates Hills homes are custom-built, so we put each exterior item to Emaar in writing before drawing it, rather than assume either answer.
06What are contractor working hours in Emirates Hills?
The Emirates Living villa rulebook, uploaded in February 2026, allows noisy works from 10:00 to 13:00 and 15:00 to 17:00, Monday to Saturday, with none on Sundays or public holidays except emergencies. Bulk deliveries need 48 hours’ notice and run from 10:00 to 13:00.
07How long does an Emirates Hills villa renovation take, and what does it cost?
Around 12 months from brief to handover: 4 weeks planning, 8 weeks design with approvals in parallel, 6–8 months build and 2 weeks handover. Villa renovation in Dubai runs AED 420–1,400 per sqft of built-up area, and our villa budgets start from AED 1M.
Sources
Sources, and when we last checked them.
Last reviewed 16 October 2026. Every rule, fee and time on this page is as published by the body named, on the date shown, except figures marked as from Fajr’s 2026 applications, which are first-hand estimates. Rules and fees change: confirm each at application.
All 17 sources, with linksClose the detail
Official sources
- Emaar, Home Modifications – Dubai factsheet, 2022, accessed 16 Oct 2026
- Emaar Community Management, Emirates Hills (Emirates Living residences), read October 2026, accessed 16 Oct 2026
- Emaar Community Management, Communities – Emirates Living, read October 2026, accessed 16 Oct 2026
- Emaar Community Management, About Emirates Living, read October 2026, accessed 16 Oct 2026
- Emaar Community Management, Guidelines – Emirates Living, read October 2026, accessed 16 Oct 2026
- Emaar Master Community Rules – Villas – Emirates Living, uploaded February 2026, accessed 16 Oct 2026
- ECM Contractors Portal, contractor registration and entry permits, accessed 16 Oct 2026
- Dubai Development Authority, Building Modification – Design, accessed 16 Oct 2026
- Dubai Development Authority, Building Modification – Permit, accessed 16 Oct 2026
- Dubai Development Authority, Building Modification – Completion, accessed 16 Oct 2026
Villa-type references: property portals and press
- Gulf News, Emaar unveils villas at Emirates Hills, 29 June 2005, accessed 16 Oct 2026
- LuxuryHabitat, Head to the hills, 17 October 2014, accessed 16 Oct 2026
- Betterhomes, Emirates Hills area guide, read October 2026, accessed 16 Oct 2026
- Bayut, Popular sectors to buy a villa in Emirates Hills, updated 16 October 2026, accessed 16 Oct 2026
- Property Finder, Emirates Hills Sector L area insights, read October 2026, accessed 16 Oct 2026
- Property Finder, Emirates Hills Sector W area insights, read October 2026, accessed 16 Oct 2026
First-hand: Fajr Interiors projects and 2026 applications
- Fajr Interiors, our own 2026 applications in Dubai communities, including Emaar, Nakheel, Emirates Hills, Tilal Al Ghaf and Al Barari submissions (first-hand, not an official schedule), as at 16 Oct 2026
Related
Other villa communities, and the guides.
Dubai Hills
Emaar
Renovating here? →The Springs & Meadows
Emaar
Renovating here? →Jumeirah Islands
Nakheel
Renovating here? →Arabian Ranches
Emaar
Renovating here? →Palm Jumeirah
Nakheel
Renovating here? →Al Barari
Al Barari
Renovating here? →District One
Meydan
Renovating here? →Tilal Al Ghaf
Majid Al Futtaim
Renovating here? →All of Dubai
The method, the approvals and the numbers for every villa community we work in.
Villa renovation in Dubai →
Villa renovation · Emirates Hills
Start your Emirates Hills villa in the right order.
Tell us the sector, the size of the house and what you want changed. We’ll come back with a scope, the Emaar and DDA route for your plot and a straight number, and a date for the site survey. Villa budgets start from AED 1M.
Since 2011 · 50+ projects · Trade licence 648890 · G+1 approved contractor (DM) · Registered with Emaar and Nakheel