Villa renovation in Dubai Hills — NOC first, then the build.
In Dubai Hills Estate, villa work beyond internal painting, furniture and maintenance needs an Emaar NOC first, then a DDA Building Modification permit, and a completion inspection before Emaar releases the deposit. Fajr Interiors is a Dubai Hills villa renovation company: we draw, lodge and build that route under one contract, with the interior design included; Villa 47 Fairways here took 12 months for 10,000 sqft.
Last reviewed 1 Oct 2026Sources and dates

At a glance
Dubai Hills, at a glance.
- Community management
- Emaar Community Management (ECM)6
- NOC issued by
- Emaar, through the Home Modifications service3
- Where to apply
- Dubai Hills Estate community portal on ecm.ae; contractors at ecmpermits.ae8
- Main villa types
- Sidra, Maple townhouses, Club Villas, Golf Place, Fairway Vistas
- Handover era
- From 2016 (Hills Grove); Sidra and Maple from 201912
- Not covered
- Custom villas on Dubai Hills Plots sit outside Emaar’s standard NOC service1
Approvals · Dubai Hills
The Dubai Hills approval route, in six steps.
Emaar reviews a Dubai Hills villa alteration first; DDA then approves the design, issues the permit and signs off completion.
Step 01 / 06
Check the scope against Emaar’s list
- Issued by
- Fajr Interiors, at the site survey
- Where
- Your villa
- You receive
- A scope, as-built drawings and the documents list
What to know
Emaar lists internal painting, furniture, electrical fixtures and regular maintenance as needing no NOC.1 Anything else in Dubai Hills, from a carport to a new kitchen layout, goes to Emaar first.
Step 02 / 06

Step 03 / 06


DDA Building Modification – Design
- Issued by
- DDA; the consultant applies
- You receive
- Stamped, approved drawings
What to know
DDA asks for the approved drawings, the proposed changes highlighted, structural calculations where relevant, and a Dubai Civil Defence NOC where fire and life safety systems change.9
Step 04 / 06

DDA Building Modification – Permit
- Issued by
- DDA; the contractor applies
- You receive
- The building modification permit
What to know
The application carries an appointment letter signed by the owner, consultant and contractor, and a site mobilisation layout where one applies.10
Step 05 / 06

ECM contractor entry permit
- Issued by
- Emaar Community Management
- Where
- ecmpermits.ae
- You receive
- An entry permit for this community and contract
What to know
The contractor registers with its trade licence and the manager’s passport and Emirates ID.8
Step 06 / 06



Completion, then the deposit
- Issued by
- Emaar, then DDA
- Where
- Community portal; DDA Building Modification – Completion
- You receive
- Emaar’s inspection approval, the DDA completion certificate and the deposit refund
Read the detailClose the detail
Dubai Hills is a young community, and most briefs we see here are upgrades to the developer finish rather than structural work. That keeps many jobs at the Emaar NOC and the ECM entry permit. The moment a scope moves walls, adds area or changes services, the DDA design and permit steps apply as well.
We lodge the Emaar submission as soon as the layout is signed, so the DDA design review runs inside the 8-week design stage, not after it.1
One exception needs care. Emaar’s factsheet says its standard NOC service does not apply to “Dubai Hills Plots”.1 If your villa was custom-built on a plot rather than bought from a cluster, the route is confirmed with Emaar before anything is drawn.
Documents
What goes into a Dubai Hills submission.
Emaar publishes a short checklist; DDA adds its own for design, permit and completion. We assemble both sets from one survey.
Concept visualisationYou provide
- Title deed and owner ID
- Photos of the areas to change, or access for ours1
- Earlier NOCs, if the villa has been altered
We prepare
Read the detailClose the detail
A DDA design application needs the approved drawings of the villa as built, which is why the survey measures the house rather than trusting the handover set.9
Fees and timelines
Published fees and timelines for a Dubai Hills villa.
These are the figures Emaar and DDA publish themselves, each with its date. Confirm every one at application.
The villa programmeAround 12 months, brief to handover
| Item | Figure | Timing | Charged by | Source |
|---|---|---|---|---|
| Emaar NOC · review fee | AED 500 | Paid when you apply; non-refundable | Emaar | As published by Emaar, April 2022. Source 1. Confirm at application. |
| Emaar NOC · approval fee | AED 1,000 minor works · AED 2,000 major works | 3 business days from a complete submission; the review fee is deducted | Emaar | As published by Emaar, April 2022. Source 1. Confirm at application. |
| Landscaping, paving or external paint NOC | AED 100 | 2 business days | Emaar | As published by Emaar, April 2022. Source 1. Confirm at application. |
| Security deposit | AED 5,000, refundable | Refunded after the completion inspection; claim within two years of payment | Emaar | As published by Emaar, April 2021. Source 2. Confirm at application. |
| Added GFA or BUA on an extension | Charged; the rate is not published | Quoted by Emaar with the application | Emaar | As published by Emaar, April 2022. Source 1. Confirm at application. |
| DDA Building Modification – Design | AED 1,500 + AED 10 Knowledge + AED 10 Innovation Dirham | 5 working days; approved design valid 6 months | DDA | As published by DDA, September 2026. Source 9. Confirm at application. |
| DDA Building Modification – Permit | AED 1 per sq ft of added or relevant BUA + AED 20 | 2 working days; renewal AED 200 per 3 months, up to 1 year | DDA | As published by DDA, September 2026. Source 10. Confirm at application. |
| DDA Building Modification – Completion | No fee for a standard submission | 3 working days | DDA | As published by DDA, September 2026. Source 11. Confirm at application. |
Read the detailClose the detail
Fees quoted on contractor sites for Dubai Hills vary widely; they are not Emaar’s figures. Emaar’s own factsheet confirms that added GFA or BUA is charged, but does not publish the rate, so we ask for it in writing with the application.1
The deposit amount is from Emaar’s 2021 factsheet.2 DDA’s pages are undated, so they show the month we read them.
What’s allowed
What you can do in a Dubai Hills villa, and what needs Emaar.
Emaar’s Dubai Hills FAQ and the villa rulebook split every job three ways. Each chip links to its source.
Allowed without an NOC4
Needs approval first8
Read the detailClose the detail
Emaar assesses extensions case by case, townhouses included. Our 2026 approval in The Springs capped the extension at about 10% of the existing BUA, with other conditions.17 Emaar’s 2022 factsheet listed townhouse extensions as restricted;1 a Maple extension is drawn and put to Emaar before it is priced.
“Changes to the exterior of the villa are not permitted” is the Dubai Hills FAQ wording.3 The garden, the pool and shade can still change with an NOC.
Rules on site
Rules on site in Dubai Hills.
The Dubai Hills villa rulebook, uploaded in March 2026, sets the hours below. Noisy work outside them earns a notice of violation.
The working daySource 4
- Monworks
- Tueworks
- Wedworks
- Thuworks
- Friworks
- Satworks
- Sunno works
Entry permits
Contractors enter only with an approved ECM entry permit; the community manager can refuse access.4
Deliveries
48 hours’ notice for bulk deliveries, Monday to Saturday, 10:00–13:00 only.4
Debris
Removed the same day, at the owner’s cost; packing never left overnight.4
Common areas
Dust contained and paths protected; damage is reinstated at the owner’s cost.4
NOC on display
The Emaar NOC stays on display for the length of the works.4
Penalties
A notice of violation, then fines on the service-fee account; ECM’s contractor portal lists fines up to AED 5,000.8
Read the detailClose the detail
ECM’s contractor portal gives different hours, 08:00 to 17:30 with Fridays off.8 The villa rulebook is the newer document and names Sundays as the rest day, so we plan to it and confirm with the community manager at mobilisation. Ramadan hours are not stated in the rulebook.
Villa types
Dubai Hills villa types, and what each usually needs.
Dubai Hills was handed over from 2016, so most villas here need an upgrade of the developer finish rather than new services.
Townhouses
Maple 1, 2 and 3
- Bedrooms
- 3–5 bed
- Handover
- From 201914
Typical renovationOpen kitchens, wardrobes and stair joinery; an extension goes to Emaar on application.
Villas
Sidra 1, 2 and 3
- Bedrooms
- 3–5 bed
- Handover
- Handed over 201913
Typical renovationKitchen and family room joined up, the developer finish replaced, a pool added with an NOC.
Villas in five design styles
Club Villas
- Bedrooms
- 3–4 bed
- Handover
- Not published15
Typical renovationJoinery, lighting and landscape to match the chosen style, inside the fixed exterior.
Golf-course villas
Golf Place
- Bedrooms
- 4–6 bed
- Handover
- Not published7
Typical renovationStone, joinery and lighting upgrades; terraces and shade toward the course.
Golf villas with private pool
Fairway Vistas
- Bedrooms
- 6–7 bed
- Handover
- Not published16
Typical renovationWhole-house interiors at villa scale, often phased by floor.
Custom-built villas
Dubai Hills Plots
- Bedrooms
- By design
- Handover
- Varies
Typical renovationRoute confirmed with Emaar first: its standard NOC service excludes plots.1
Read the detailClose the detail
Hills Grove saw the first Dubai Hills handovers in mid-2016; Sidra and Maple followed in 2019.12 Palm Hills and Emerald Hills were still under development when the portals we cite were written. Bedroom counts come from property portals, not Emaar.
Common projects
What Dubai Hills owners ask us to change.
Young villas, built to a developer standard: the work here is about finish, joinery and the garden, not replacing tired services.

Developer kitchens, replaced
The most common first request. Open the wall to the family room and it becomes an alteration Emaar reviews.

Wardrobes and joinery
Basic wardrobes are where a young villa gains most: made-to-measure joinery, drawn to its walls.

Pools and gardens
Pools, pergolas and shade need an Emaar NOC.3 We draw the garden with the house, in one submission.
- On application
Maple: extensions on application
Emaar assesses townhouse extensions case by case.17 We draw the extension and a ground-floor replan side by side.
- Exterior fixed
An exterior that stays as built
The façade, windows and colour stay as Emaar built them.3 Light, glazing reveals and interior joinery do the work instead.
Proof in Dubai Hills
Villa 47 Fairways, with its owner.
Villa 47 Fairways is a 10,000 sqft Dubai Hills villa Fajr Interiors delivered over 12 months. Its owner, Wyll, walked through the finished house with us on film; this still is from that walkthrough.

Best decision I made was to hire Fajr Interiors.
- Area
- 10,000 sqft
- Programme
- 12 months
- Community
- Dubai Hills
Dubai Hills
A Dubai Hills villa by Fajr, room by room.
Rooms from a Dubai Hills villa by Fajr Interiors, shown in our portfolio: settled on drawings and physical samples before anything was ordered.

VillaA Dubai Hills villa by Fajr 
LivingLiving room 
Powder roomPowder room 
DressingDressing room entrance
Tap a room to enlarge it.
The full portfolio →Cost
What a Dubai Hills renovation costs.
Villa renovation in Dubai runs AED 420–1,400 per sqft of built-up area, and our villa budgets start from AED 1M. Where a Dubai Hills villa lands depends on the scope and the finishes; the figure is a line-by-line quote against drawings, never a rate.
Dubai Hills FAQ
Before you renovate in Dubai Hills.
Villa renovation FAQ — Dubai Hills, Dubai.
The questions Dubai Hills owners ask before a survey, answered from Emaar’s and DDA’s own pages.
01Do I need an Emaar NOC to renovate my villa in Dubai Hills Estate?
Yes, for anything beyond internal painting, furniture, electrical fixtures and regular maintenance, which Emaar lists as NOC-free. Carports, garden pergolas, pool renovations and any other alteration go through Home Modifications on the Dubai Hills Estate community portal before any authority submission is made.
02Which authority issues the building permit for a Dubai Hills villa?
The Dubai Development Authority. After the Emaar NOC, the consultant applies for DDA Building Modification – Design and the contractor for the Building Modification – Permit. Dubai Civil Defence joins only where fire and life safety systems change, and DDA closes the job with a completion certificate.
03How long does the Emaar NOC take in Dubai Hills?
Emaar’s factsheet gives three business days for minor and major works and two for soft landscaping or external painting, counted from a complete submission. Treat those as published targets and confirm them at application. A missing drawing or photo restarts the clock, so we submit complete sets.
04Can I extend my villa in Dubai Hills Estate?
Yes, on application. Emaar assesses each extension case by case, Maple townhouses included, and charges for the added area; DDA then issues the permit. On our 2026 Springs approval Emaar capped the extension at about 10% of the existing BUA. Custom villas on Dubai Hills Plots sit outside Emaar’s standard NOC service.
05Can I change the exterior or add solar panels to my Dubai Hills villa?
Emaar’s Dubai Hills FAQ says changes to the villa exterior are not permitted. The rulebook prohibits solar panels visible from common areas or neighbouring plots, and awnings or shade need written approval in materials that match the villa. We check each exterior item before drawing it.
06What are contractor working hours in Dubai Hills?
The Dubai Hills villa rulebook, uploaded in March 2026, allows construction from 10:00 to 13:00 and 15:00 to 17:00, Monday to Saturday, with no works on Sundays or public holidays except emergencies. Bulk deliveries need 48 hours’ notice and run from 10:00 to 13:00.
07How long does a Dubai Hills villa renovation take, and what does it cost?
Around 12 months from brief to handover: 4 weeks planning, 8 weeks design with approvals in parallel, 6–8 months build and 2 weeks handover. Villa 47 Fairways took 12 months for 10,000 sqft. Villa renovation in Dubai runs AED 420–1,400 per sqft of built-up area.
Sources
Sources, and when we last checked them.
Last reviewed 1 October 2026. Every rule, fee and time on this page is as published by the body named, on the date shown, except figures marked as from Fajr’s 2026 applications, which are first-hand estimates. Rules and fees change: confirm each at application.
All 17 sources, with linksClose the detail
Official sources
- Emaar, Home Modifications – Dubai factsheet, 2022, accessed 30 Sep 2026
- Emaar, Home Modifications fact sheet, 12 April 2021, accessed 30 Sep 2026
- Emaar Community Management, Home modifications FAQ – Dubai Hills Estate, accessed 30 Sep 2026
- Emaar Master Community Rules – Villas – Dubai Hills Estate, uploaded March 2026, accessed 30 Sep 2026
- Emaar Community Management, Rules and regulations – Dubai Hills Estate, accessed 30 Sep 2026
- Emaar Community Management, Dubai Hills Estate, accessed 30 Sep 2026
- Emaar, Dubai Hills Estate, accessed 30 Sep 2026
- ECM Contractors Portal, contractor registration and entry permits, accessed 30 Sep 2026
- Dubai Development Authority, Building Modification – Design, accessed 30 Sep 2026
- Dubai Development Authority, Building Modification – Permit, accessed 30 Sep 2026
- Dubai Development Authority, Building Modification – Completion, accessed 30 Sep 2026
Villa-type references: property portals and press
- Propsearch, Dubai Hills Estate, accessed 30 Sep 2026
- fäm Properties, Sidra Villas, accessed 30 Sep 2026
- fäm Properties, Maple at Dubai Hills Estate, accessed 30 Sep 2026
- Bayut, Club Villas area guide, accessed 30 Sep 2026
- LuxuryHabitat, Fairways Vistas, accessed 30 Sep 2026
First-hand: Fajr Interiors projects and 2026 applications
- Fajr Interiors, our own 2026 applications: Emaar extension approval in The Springs and Nakheel committee estimates (first-hand, not an official schedule), as at 1 Oct 2026
Related
Other villa communities, and the guides.
Villa renovation · Dubai Hills
Start your Dubai Hills villa in the right order.
Tell us about the villa: its cluster, the size and what you want changed. We’ll come back with a scope, the Emaar and DDA route mapped for your plot and a straight number, and a date for the site survey. Villa budgets start from AED 1M.