Render of the reception at Opus by Omniyat, Opus Tower, Dubai

Workplace / Opus Tower

The office at Opus by Omniyat.

Opus by Omniyat is a 6,200 sqft executive office in Opus Tower, Dubai, contracted at AED 4.5M, or AED 726 per sqft, and in its final weeks before handover. It was specified to be sold on, so function was priced before finishes, and glass carried borrowed light to a dark core. Fajr also fitted out Global Textiles and International Materials in Opus Tower.

Reception · render

Opus TowerOpus by Omniyat, Dubai
6,200 sqftExecutive office floor
Final weeksBefore handover
AED 4.5MProject value
AED 726 / sqftAED 4.5M across 6,200 sqft
Approved listOpus Tower contractor

Project context

The building, the brief, the budget.

Opus by Omniyat is a Dubai tower with its own fitout rules, and we are on its approved contractor list. The floor inside it was built as an investment: 6,200 sqft, specified to be sold on, contracted on a fixed budget against a 24-week programme.

Render of the reception at Opus by Omniyat, Opus Tower, Dubai

The design · render

Reception at Opus Tower

The reception as designed: timber-lined walls, a stone-fronted desk and a lit ceiling cove, with glass to the rooms beyond.

Building
Opus TowerOpus by Omniyat, Dubai
Area
6,200 sqft
Programme
24 weeksContracted · 4 + 2 + 16 + 2
Budget
FixedValue-engineered against
Brief
InvestmentSpecified to be sold on

The brief

The money had to show in how the floor works.

The client wanted a high-end workplace built as an investment. Because the floor was specified to be sold on, the money had to show first in how the floor works — the plan and the light — and only then in finishes. The budget was fixed, and the floorplate had very little natural light.

Open office floor at Opus by Omniyat: glass partitions along the core and a lit ceiling cove carrying daylight inward

The project file, in three lines

  • BriefA high-end workplace built as an investment — specified to be sold on, so the money had to show in how the floor works before it showed in finishes.
  • ConstraintA fixed budget to value-engineer against, on a floorplate with very little natural light.
  • SolutionFunction priced first, then materials — still high spec, never at the expense of the plan. Glass partitions wherever the layout allowed, so borrowed light reaches the core, and a lighting study behind every fitting specified.

Start to finish

From the first survey to the final layer.

The project in the order it happened: the floor as we found it, the layouts we tested, the renders and elevations the client signed, the materials chosen before anything was ordered, and the build itself.

01

Survey

The floor as we found it.

We measure and photograph the floor before any drawing: the core, the columns, the glazing, the ceiling height and the services.

02

Space planning

Three layouts, then one.

Three layouts tested the same brief against the floorplate. The client chose one, and it became the plan we built.

Final furnishing plan of the Opus Tower office by Fajr Interiors: reception and lounge at the core, boardrooms, CEO and director rooms along the glazing, two workstation zones, meeting rooms and pantries
The final plan · furnishing layout
03

3D design

Every room, before it was built.

Fourteen renders of the agreed plan, room by room, so the client saw the finished floor before a material was ordered.

Render of the Opus Tower office by Fajr Interiors: reception
Reception
Render of the Opus Tower office by Fajr Interiors: meeting rooms behind glass
Meeting rooms behind glass
Render of the Opus Tower office by Fajr Interiors: reception and the glass offices
Reception and the glass offices
Render of the Opus Tower office by Fajr Interiors: reception bench and phone booth
Reception bench and phone booth
Render of the Opus Tower office by Fajr Interiors: lounge and glass meeting room
Lounge and glass meeting room
Render of the Opus Tower office by Fajr Interiors: workstations
Workstations
Render of the Opus Tower office by Fajr Interiors: boardroom
Boardroom
Render of the Opus Tower office by Fajr Interiors: boardroom table
Boardroom table
Render of the Opus Tower office by Fajr Interiors: private office
Private office
Render of the Opus Tower office by Fajr Interiors: private office
Private office
Render of the Opus Tower office by Fajr Interiors: private office
Private office
Render of the Opus Tower office by Fajr Interiors: private office
Private office
Render of the Opus Tower office by Fajr Interiors: ceo room, lounge
CEO room, lounge
Render of the Opus Tower office by Fajr Interiors: ceo room, desk
CEO room, desk
04

Rendered elevations

The walls, to scale.

Rendered elevations of the main walls: joinery, glass and finishes drawn to scale, so what was signed is what was built.

05

Material selection

Chosen with the client, signed before ordering.

Veneers, stone, fabrics and metals, chosen with the client and signed off before any order was placed.

Watch the selection
Fajr Interiors design team laying out timber, stone and carpet samples on the bare concrete floor of the Opus Tower office
Samples on the stripped-back floor
Material samples for the Opus by Omniyat office: a travertine block, cream bouclé, mahogany veneer, brushed brass and leather swatches on the studio table
Travertine, veneer and leather
Upholstery samples for the Opus by Omniyat office: green tweed, cognac and brown leathers, cream bouclé and a run of camel and taupe swatches
Leathers and fabrics
The Opus by Omniyat material board from above: black and bronze metal plates, a brushed brass plate and a bronze chair-leg finish among leathers, travertine and veneer
Metals and finishes
06

Execution

Built to the signed drawings.

Partitions, ceilings and services built to the drawings the client signed, with the design team back on site as the floor took shape.

Fajr Interiors site team in hi-vis vests building drywall partitions and ceiling bulkheads in the Opus Tower office
Partitions and ceilings going in
Fajr Interiors team walking the Opus Tower office during the build, ducts and ceiling framing overhead and the site team at work behind
Walking the site mid-build
The Fajr Interiors team on site at the Opus Tower office during the build
On site during the build
Behind the scenesWith the client, in our studio and on site

Behind the scenes

With the client, in our studio and on site.

Short clips from the project, in the order the work happened: the first walkthrough of the empty floor, the layout and material sessions in our studio, the client's approvals and site visits, and the site as it was built, from MEP and ceilings to the GRC panels, the lighting controls and the final layer.

First walkthrough: Opus Tower office fitout by Fajr Interiors, Dubai

On site

First walkthrough

The bare floor walked with the team, the room lines marked out on the slab.

The floor and the design: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 6 June

The floor and the design

The empty floor walked through, and the design it would become.

MEP complete: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 29 June

MEP complete

Walking the floor with the MEP work complete.

Above the ceiling: Opus Tower office fitout by Fajr Interiors, Dubai

On site

Above the ceiling

Services and acoustic baffles in place above the ceiling, before it closes.

Ceiling lights: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 3 July

Ceiling lights

The ceiling coves and light fittings taking shape.

Client visit: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 15 July

Client visit

The client on site as the partitions and timber panels went in.

Layout direction: Opus Tower office fitout by Fajr Interiors, Dubai

Our studio · 20 July

Layout direction

The layout worked out on paper and on screen, then talked through with the client.

In the studio: Opus Tower office fitout by Fajr Interiors, Dubai

Our studio

In the studio

Drawings, samples and the design team at work on the floor.

Material selection: Opus Tower office fitout by Fajr Interiors, Dubai

Our studio · 30 July

Material selection

Veneers, fabrics, metals and stone, chosen with the client.

Client approvals and visits: Opus Tower office fitout by Fajr Interiors, Dubai

Our studio · On site

Client approvals and visits

Approvals with the client in our studio, then the client walking the site as the build went in.

Execution begins: Opus Tower office fitout by Fajr Interiors, Dubai

On site

Execution begins

Partitions and ceilings going up, room by room, to the signed drawings.

Glass partitions going in: Opus Tower office fitout by Fajr Interiors, Dubai

On site

Glass partitions going in

The glass partitions lifted and set into place.

Curved glass: Opus Tower office fitout by Fajr Interiors, Dubai

On site

Curved glass

The curved glass in place, before its protective film comes off.

GRC panelling: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 5 August

GRC panelling

The sculpted GRC wall panels, from the design to the wall.

Client visit: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 11 August

Client visit

The client walking the ceiling coves and the lighting as they took shape.

DALI lighting: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 20 August

DALI lighting

The DALI lighting controls, tested on site.

Automation: Opus Tower office fitout by Fajr Interiors, Dubai

On site

Automation

The automation panel and its controls, explained on site.

Final layer: Opus Tower office fitout by Fajr Interiors, Dubai

On site

Final layer

Ceilings, lighting and the last finishes going in.

Site update: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 3 September

Site update

The finished ceilings and the glass rooms, walked with the client.

Near the finish: Opus Tower office fitout by Fajr Interiors, Dubai

On site · 15 September

Near the finish

A walk through the meeting rooms, the custom lighting and the workstations.

Clip to come

Our studio

Design work

The design team detailing the floor.

Three decisionsOrder, glass, light

Key decisions

Three decisions that made the budget work.

A fixed budget on a dark floorplate can fail two ways: money spent on finishes the plan cannot carry, or rooms built that trap what little light there is. Three decisions kept Opus clear of both. The clips show the same kinds of work on other Fajr office sites.

Site meeting on a Fajr Interiors office fitout, joinery going up, Dubai

Clip · another Fajr office site

Value engineering

Function priced first, then materials

The plan, the partitions and the services were costed before a finish was chosen: still high spec, never at the expense of the plan.

Fixed budgetPlan firstHigh spec

Glass partitions installed on a Fajr Interiors office fitout, Dubai

Clip · another Fajr office site

Borrowed light

Glass wherever the layout allowed

Glass partitions wherever the layout allowed, so borrowed light reaches the core of a floorplate with very little natural light.

Glass partitionsBorrowed lightThe core

Open ceiling services and acoustic baffles on a Fajr Interiors office fitout, Dubai

Clip · another Fajr office site

Lighting

A lighting study behind every fitting

No fitting was specified without a lighting study behind it, so the artificial light was planned to do the work the façade could not.

Lighting studyEvery fittingBefore ordering

On siteOpus Tower · joinery in progress
Project update: Opus Tower office fitout, joinery in progress, DubaiInstagram

On site · Opus Tower

Joinery going in, on the Opus floor.

Joinery is where a fixed budget gets tested: made-to-measure pieces carry a lead time of around eight weeks, so they are ordered against a signed plan or the programme moves. This project update from Opus Tower shows the joinery going in on site, inside the 16-week build.

Where
Opus Tower
Stage
Build · 16 weeks
Work
Joinery in progress
Lead time
~8 weeks, made joinery

Open the post to watch the project update from the floor.On the programme

ProgrammeThe contracted programme

Programme · done in the right order

The contracted programme, as a sequence.

Opus was contracted on 24 weeks: 4 weeks of space planning, 2 of approvals, 16 of build and 2 to furnish, each at the short end of our standard office ranges, with the approvals inside the programme rather than after it. The floor is now in its final weeks before handover.

24weeks
contracted
4Space
planning
2Approvals
16Build
2Furnish

The bars show the 4 + 2 + 16 + 2 week stage sequence, not a trade-by-trade schedule. On a phone, swipe the programme sideways.

InvestmentWhat it cost, and what that covers

Investment

What it cost, fenced by what it covers.

Opus by Omniyat cost AED 4.5M across 6,200 sqft, which is AED 726 per sqft. It is one of the two executive floors behind our published office rates, and it sits inside the turnkey band, not above it: what separates one floor from another is control and sequence, not price.

Project value

AED 4.5M6,200 sqft · executive office floor

Delivered rate

AED 726 / sqftAED 4.5M across 6,200 sqft

An office fitout in Dubai starts at AED 350 per sqft for shell-to-occupied — partitions, ceilings, flooring, MEP alterations and joinery. Turnkey, with FF&E, IT, AV, automation and appliances included, runs AED 600–850 per sqft. Our last two executive floors landed at AED 726 and AED 840.

Where Opus sits in the turnkey band

Opus by Omniyat · AED 726 per sqft, AED 4.5M across 6,200 sqft. IMI at One Za’abeel, the other executive floor, landed at AED 840 per sqft.

A floor like this? Start with the size and the date.

Opus’s figure, not a quotation. Every project is priced on its own scope.

QuestionsSize, time, cost, light

FAQs

Questions we get. Answered.

The questions office clients ask most about Opus by Omniyat: how big it is, how long it took, what it cost, how the budget was held and how light reached the core. Every answer uses verified project figures, and every price is stated with the scope it covers.

How big is the Opus by Omniyat office?

The office is 6,200 sqft in Opus Tower, the Opus by Omniyat building in Dubai. It is an executive workplace built as an investment and specified to be sold on, so the floor had to prove its value in how it works: the plan, the rooms and the light, before any of the finishes.

What programme was the Opus fitout contracted on?

Twenty-four weeks: 4 weeks of space planning, 2 weeks of approvals, 16 weeks of build and 2 weeks to furnish, with the approvals inside the programme rather than after it. The floor is now in its final weeks before handover.

What did the Opus office cost?

An office fitout in Dubai starts at AED 350 per sqft for shell-to-occupied — partitions, ceilings, flooring, MEP alterations and joinery. Turnkey, with FF&E, IT, AV, automation and appliances included, runs AED 600–850 per sqft. Our last two executive floors landed at AED 726 and AED 840. Opus by Omniyat is the AED 726 floor: AED 4.5M across 6,200 sqft.

How do you value-engineer without losing quality?

On Opus the order was fixed: function priced first, then materials — still high spec, never at the expense of the plan. With a fixed budget to value-engineer against, what the floor had to do was costed before any finish was chosen, so the materials were chosen against the plan, not the other way round.

How do you light an office floor with little daylight?

Glass partitions wherever the layout allowed, so borrowed light reaches the core, and a lighting study behind every fitting specified. The Opus floorplate had very little natural light, so the partitions were planned to pass light through rather than stop it, and no fitting went in without the study behind it.

Is Fajr Interiors approved to work in Opus Tower?

Yes. We are on the approved contractor list at Opus Tower, as we are at One Za’abeel, Vision Tower and Emaar Square. That matters because every tower runs its own fitout rules, access and inspection regime, and the application is lodged by the contractor the building has approved.

Can’t find what you’re looking for?Our team is here to help with anything you need to know.
Call us+971 800 3257
Email ushello@fajrinteriors.com
WhatsApp usMessage the studio

Start in the right order

Your floor. Done in the right order.

Tell us the floor, the team and the move-in date. We will map the scope, the approval route and the programme before detailed pricing.